Project
name: Soft start systems and motor
controls for nine pump motors at the Dokan-Sulaymaniyah
Dam.
Client: GULF REGION DIVISION-CENTRAL
DISTRICT W6EX GRD CENTRAL DISTRICT KO OPERATION
IRAQI FREEDOM APO AE IRAQ
POC: Salo, Tera L TAG,
E-mail: Tera.L.Salo@usace.army.mil
POC: Brady, John TAG Contractor,
E-mail: John.Brady@usace.army.mil
Description:
Engineering, design review, construction,
commissioning, operation and training of
new, completely operational, soft start
systems and motor controls for nine pump
motors at the Dokan-Sulaymaniyah Dam. The
system will include all necessary connections,
controls and cabling for a complete soft
start system for these pumps for 3 pump
stations. The system is designed and manufactured
by German Company MOCOTECH. The system contains
the following:
LS 1 Pump: Supply soft
starter system including all requirements,
for operating motors of 3 IDP Pumps (12
kV) including cables and capacitor bank
for correction over factors. Specifications
as follows: 850 kW, Power factor: 0.83,
Line Voltage: 11kV, Type: Squirrel Cage,
Manufacturer: ABB, Motor Current: 54.4A,
Soft Starter Current:140A, PFC selected:
350 kVA.
LS
2 PUMP: Supply soft starter system
including all requirements , for operating
motors of 3 IDP Pumps (12 kV) including
cables and capacitor bank for correction
over factors. Specifications as follows:
1,500 kW, Power factor : 0.87, Line Voltage:
11kV, Type: Squirrel Cage, Manufacturer:
ABB, Motor Current: 90.47A, Soft Starter
Current:140A, PFC selected: 400 kVA.
LS
3 PUMP: Supply soft starter system
including all requirements , for operating
motors of 3 IDP Pumps (12 kV) including
cables and capacitor bank for correction
over factors. Specifications as follows:
1,720 kW, Power factor : 0.86, Line Voltage:
11kV, Type: Squirrel Cage, Manufacturer:
ABB, Motor Current: 105A, Soft Starter Current:140A,
PFC selected: 500 kVA.
Staff
details: A site office with highly
experienced engineers and technicians managing
the site activity was established. Outside
Iraq, offices supported the project by purchasing
equipment. The Irbil and Germany offices
both supported vital administration and
correspondence needs. The site staff was
entirely comprised of locals from Dokan
& Sulaymaniyah, 80 of skilled and unskilled
workers, a total of 10 engineers, 15 technicians
and 8 administrative support staff were
all part of the successful performing of
this project.
Starting
Date: August 2010
End Date: 7-April-2011