Project
name: 3D Siesmic Project Zubair
Iraq: UXO Identification and Clearance.
Client: BGP Inc., China
National Petroleum Corporation.
POC: Attn: Mr. Yu Runchang,
Mob.: 00964-781-3451638, Email: yurunchang@gmail.com
Description:
BGP project contains services to carry out
3D seismic project in the Zubair Block in
Southern Iraq. The total size of the project
concession area is 1,993 square kilometers.
Danube Demining &
UXO Clearance is providing UXO clearance
plan to clear the following:
1. Total length of receiver lines is about
8,200 km.
2. Total length of source lines is about
8,200 km.
3. Interval of receiver lines and source
lines both are 250 meter.
4. Total area of clearance will be 16,400
km length.
5. Receiver and Source line width of clearance
will be 10 meters wide with degradable plastic
bag make of each side of central line.
6. Specific Client requests - 70km per day,
on average, should be the clearance goal
(Exception for work in mined areas).
Staff
details: The site staff contains
more than 100 deminers and demining experts,
supported by 10 medics, 8 administration
and 10 logistic workers.
Offices in Baghdad and Basrah with high
skilled staff are supporting the site activities.
Outside Iraq offices are supporting the
project by purchasing equipment and instruments.
Most modern equipment, large loops, detectors,
surveying equipment were used.
Two partners, local companies Abraj Al Battat
and Hoor are supporting the management and
successful performing of the project.
Starting
Date: October 2011
Completion Date: Work
in Progress